National Grid

Department for Energy Security and Net Zero written question – answered at on 21 January 2025.

Alert me about debates like this

Photo of Lord Spellar Lord Spellar Labour

To ask His Majesty's Government what is their latest estimate of delivery times for equipment to expand capacity on the electricity grid, including high voltage cable, pylons, large power transformers and circuit breakers.

Photo of Lord Hunt of Kings Heath Lord Hunt of Kings Heath Minister of State (Department for Energy Security and Net Zero)

Through engagement with electricity operators, we are aware of estimated lead times for grid components. Due to growing cross-industry demand, lead times have increased, for example, to 24-months for 132kV transformers and to four years for 400kV transformers and network cabling.

We continue to support Ofgem’s developing Advanced Procurement Mechanism (launching early this year) which will allow transmission operators to access constrained equipment earlier in project development.