Electricity Interconnectors

Department for Energy Security and Net Zero written question – answered at on 17 April 2024.

Alert me about debates like this

Photo of Andrew Rosindell Andrew Rosindell Conservative, Romford

To ask the Secretary of State for Energy Security and Net Zero, what her Department's policy is on the future capacity of new electricity interconnectors in (a) 2025, (b) 2030 and (c) 2040.

Photo of Justin Tomlinson Justin Tomlinson Minister of State (Department for Energy Security and Net Zero)

As of March 2024, Great Britain has 9.8GW interconnection capacity in operation. A further 1.9 GW of interconnection is in construction, with 0.5GW expected to be operational by 2025. Anticipated interconnection capacity by 2025 is therefore approximately 10.3GW.

In 2020, the Government set an ambition to realise at least 18GW of interconnection by 2030; this was reaffirmed in 2023.

Two additional interconnectors, totalling 3.2GW, have recently received positive interim regulatory decisions from Ofgem. If progressed, Great Britain will be on track for 13.1GW of interconnection capacity by 2030, and 14.9GW by 2031.

The Government will provide more information on interconnection post-2030 in due course.