To ask the Secretary of State for Business, Energy and Industrial Strategy, how much of the estimated cost of each of the following undersea electricity transmission cables will ultimately be funded through electricity bills to residential and commercial customers (a) western link (Hunterston to Flintshire Bridge), (b) eastern link (Peterhead to Drax) and (c) Sealink 1 (Sizewell to Kent).

Photo of Greg Hands Greg Hands The Minister of State, Department for Business, Energy and Industrial Strategy

All electricity network costs approved by the independent regulator Ofgem are funded through the network charges paid by electricity suppliers and generators. Ultimately, all such costs will be met by electricity consumers through their electricity bills.