Crossrail Line: Costs

Department for Transport written question – answered at on 19 April 2022.

Alert me about debates like this

Photo of Lord Crathorne Lord Crathorne Conservative

HL7742">To ask Her Majesty's Government how much the cost of the Elizabeth Line has exceeded original forecasts.

Photo of Baroness Vere of Norbiton Baroness Vere of Norbiton Parliamentary Under-Secretary (Department for Transport)

The original funding package agreed in the 2010 Spending Review to fund delivery of Crossrail (excluding costs for trains and depots) was £14.8 billion.

Current forecast costs for completing Crossrail are £18.9 billion. This includes Network Rail On Network Works costs for surface works but exclude costs for trains and depots.