Fleet Solid Support Ships: Procurement

Ministry of Defence written question – answered at on 6 September 2021.

Alert me about debates like this

Photo of Mark Francois Mark Francois Conservative, Rayleigh and Wickford

To ask the Secretary of State for Defence, what the initial operational capability is for each of the three vessels in the Fleet Solid Support Ship programme.

Photo of Jeremy Quin Jeremy Quin The Minister of State, Ministry of Defence

The Initial Operating Capability (IOC) for the Fleet Solid Support (FSS) programme will be met through the achievement of the entry into service of the first FSS Ship and each subsequent ship will enter service at the same capability standard. The date for FSS IOC and individual ship in service dates will not be determined until the Full Business Case is submitted and will be reliant on the delivery schedule agreed when the manufacture contract is awarded.

Does this answer the above question?

Yes1 person thinks so