High Speed 2 Railway Line

Department for Transport written question – answered on 3rd September 2020.

Alert me about debates like this

Photo of Fiona Bruce Fiona Bruce Conservative, Congleton

To ask the Secretary of State for Transport, what the budget is of (a) Phase 2b east and (b) Phase 2b west of High Speed Two.

Photo of Andrew Stephenson Andrew Stephenson Assistant Whip, Minister of State (Department for Transport)

The Full Business Case for Phase One sets out the central cost estimate for the whole of Phase 2b at £39bn (including contingency). The funding allocations for HS2 including phase 2b are being reviewed as part of the Comprehensive Spending Review 2020, which is due to conclude later this Autumn.

Does this answer the above question?

Yes1 person thinks so

No2 people think not

Would you like to ask a question like this yourself? Use our Freedom of Information site.