Department for Transport written question – answered at on 21 July 2020.
To ask the Secretary of State for Transport, what steps he is taking to ensure the maximum use of rail freight for moving materials during the construction of High Speed Two.
HS2 Ltd’s Environmental Statement and Code of Construction practice states that as the ‘Nominated Undertaker’ HS2 Ltd should plan to move as much material as is reasonably practicable by Rail (or Water) before Road.
Joint industry resources (including Network Rail, the Freight Industry, and HS2 Ltd) have collaborated to develop the Materials By Rail strategy and secure every available opportunity to maximise Materials By Rail volumes and accelerate the materials delivery and removals programme.
Yes3 people think so
No5 people think not
Would you like to ask a question like this yourself? Use our Freedom of Information site.