Thameslink Railway Line: Maidstone

Department for Transport written question – answered on 8th October 2019.

Alert me about debates like this

Photo of Baroness Randerson Baroness Randerson Liberal Democrat Lords Spokesperson (Transport)

To ask Her Majesty's Government when the planned Thameslink service from Maidstone East to central London and on to Cambridge is due to commence; and how frequently that service will run.

Photo of Baroness Randerson Baroness Randerson Liberal Democrat Lords Spokesperson (Transport)

To ask Her Majesty's Government what are the reasons for the repeated delays in the introduction of the Thameslink service from Maidstone East to central London and on to Cambridge.

Photo of Baroness Vere of Norbiton Baroness Vere of Norbiton Parliamentary Under-Secretary (Department for Transport)

In September, the industry confirmed that it is not able to deliver the planned new Thameslink service from Maidstone East in December 2019. Following the timetable change in May last year, passengers suffered as the industry introduced new services that it was not ready to deliver. Since then, new processes have been introduced within the industry to ensure that timetable changes are deliverable. The industry has concluded that adding these services onto an already busy and complex railway network in December presents a real risk of delay and disruption to thousands of passengers that rely on existing services. Whilst is the right decision, in this context, to delay the introduction, the Department is committed to ensuring that the rail industry delivers a reliable all-day Thameslink service from Maidstone East to London as soon as possible.