Department for Transport written question – answered at on 4 June 2019.
To ask Her Majesty's Government what is the approximate quantity of steel rail required for the HS2 project.
As stated in the Working Draft Environmental Statement (p.136), the approximate total of steel required for the HS2 project is 1.94 million metric tonnes.
The procurements for contracts that will involve the purchase of steel have not yet concluded so no contract awards have been made. However, HS2 Ltd has already engaged with thousands of British businesses, to aid them in winning work on HS2. So far 98% of contracts for HS2, awarded directly and through the supply chain, have been won by British companies, with many more opportunities to come in the future. HS2 Ltd has let around £10bn worth of contracts and by the end of next year that will be around £20bn.
Yes0 people think so
No2 people think not
Would you like to ask a question like this yourself? Use our Freedom of Information site.