High Speed 2 Railway Line

Department for Transport written question – answered on 12th February 2019.

Alert me about debates like this

Photo of Dame Cheryl Gillan Dame Cheryl Gillan Conservative, Chesham and Amersham

To ask the Secretary of State for Transport, on what date he expects the main contractors building High Speed Two Phase 1 to commence their work.

Photo of Nusrat Ghani Nusrat Ghani Parliamentary Under-Secretary (Department for Transport), Assistant Whip (HM Treasury)

Stage 1 of the main civil works contracts were awarded in July 2017 and contractors commenced design and development work then. Stage 2 of the contracts will commence when Government authorises Notice to Proceed later in 2019 and contractors will begin civil construction activities.