Fracking: Planning Permission

Ministry of Housing, Communities and Local Government written question – answered on 7th June 2018.

Alert me about debates like this

Photo of Sammy Wilson Sammy Wilson Shadow DUP Spokesperson (Treasury), Shadow DUP Spokesperson (Work and Pensions), Shadow DUP Spokesperson (Brexit)

To ask the Secretary of State for Housing, Communities and Local Government, what the average time taken to process a shale gas exploration application was in each of the last three years.

Photo of Dominic Raab Dominic Raab Minister of State (Housing, Communities and Local Government)

Mineral Planning Authority decisions to grant or refuse planning permission for shale gas exploration proposals in England over the last three years have taken between 17 and 83 weeks, from the date of validation of that application to the date the decision was issued.