High Speed 2 Railway Line

Department for Transport written question – answered on 11th May 2018.

Alert me about debates like this

Photo of Lord Framlingham Lord Framlingham Conservative

To ask Her Majesty's Government what has been the effect on HS2 of the failure of Carillion.

Photo of Baroness Sugg Baroness Sugg Parliamentary Under-Secretary (Department for Transport)

For High Speed Two Ltd, the joint venture contracts involving Carillion were on joint and several liability terms where the contracts are underwritten by all three parties.

This means that the other parties to the contract are obliged to carry out the works in Carillion’s absence.

The transition to a two party joint venture involving Eiffage and Kier has now concluded, and there have been no impacts to delivery.