Fracking: Planning Permission

Ministry of Housing, Communities and Local Government written question – answered on 19th March 2018.

Alert me about debates like this

Photo of Lord Risby Lord Risby Conservative

To ask Her Majesty's Government what estimate they have made of the average time taken between the first planning application for a shale gas well being received and final consent being granted for drilling.

Photo of Lord Bourne of Aberystwyth Lord Bourne of Aberystwyth The Parliamentary Under-Secretary of State for Wales, Parliamentary Under-Secretary (Housing, Communities and Local Government)

Mineral Planning Authority decisions to grant or refuse planning permission for exploratory wells have taken between 17 and 83 weeks from date of validation to the date the decision was issued.