To ask the Secretary of State for Defence, with reference to the National Shipbuilding Strategy, what the timeframe is for the competition to build the Type 31e frigate.

Photo of Harriett Baldwin Harriett Baldwin The Parliamentary Under-Secretary of State for Defence

Pre-procurement activity with industry has begun and will continue into early 2018 when we plan to formally start the competitive process. We plan to award a single design and build contract in 2019, allowing us to trial and accept the first ship into service in 2023.