High Speed 2 Railway Line: Eddisbury

Department for Transport written question – answered on 19th September 2017.

Alert me about debates like this

Photo of Antoinette Sandbach Antoinette Sandbach Conservative, Eddisbury

To ask the Secretary of State for Transport, how many environmental surveys have been conducted on the proposed route of the second phase of High Speed 2 through Eddisbury; and how many land access agreements have been signed between HS2 Ltd and property owners in Eddisbury.

Photo of Paul Maynard Paul Maynard Parliamentary Under-Secretary (Department for Transport)

As of the week ending 8-9-17, approximately 217 environmental surveys had been recorded in and around the Eddisbury area.

To date, HS2 Ltd has recorded a total of 90 land access licences as having been agreed entirely or partially within Eddisbury. The corresponding number for those entirely within Eddisbury is 52.

These figures are subject to change.