Department for Transport written question – answered on 27th February 2017.

Alert me about debates like this

Photo of Louise Haigh Louise Haigh Shadow Minister (Culture, Media and Sport) (Digital Economy)

To ask the Secretary of State for Transport, if he will publish his Department's analysis of the (a) cost and (b) duration of construction of the Sheffield Meadowhall High Speed Rail station.

Photo of Andrew Jones Andrew Jones Parliamentary Under-Secretary (Department for Transport)

The construction period for Phase 2b of HS2 is 9 years, from 2024 to 2033. No detailed work has been done to look into the construction planning for stations that would be served by HS2 trains. During design of the scheme over next two years, and before the hybrid Bill is deposited, HS2 Ltd will make an estimate of the construction timescales for various elements of the programme.

We do not provide cost breakdowns for specific items of the HS2 programme due to commercial sensitivities.