The table below sets out the spend on HS2 project in each year since 2009/10. Data for 2015/16 is provisional and is currently not included, pending publication of the HS2 Ltd Accounts shortly at GOV.UK, which will set out the precise level of expenditure for 2015/16.

2009/10

£m

2010/11

£m

2011/12

£m

2012/13

£m

2013/14

£m

2014/15

£m

Total HS2

9.43

24.3

54

207.6

318.2

362.7