The total length of the tunnels is 32km and tunnelling was completed in March 2015.

19.6km of the network was constructed using a 3m internal diameter tunnel boring machine

  • Willesden to St John’s Wood 3m diameter tunnel – 7.4km

  • Wimbledon to Kensal Green 3m diameter tunnel – 12.2km.

    12.4km of the network was built using a 4m internal diameter tunnel boring machine

    - St John’s Wood to Hackney 4m diameter tunnel.