London Power Tunnels

Department for Energy and Climate Change written question – answered on 26th May 2016.

Alert me about debates like this

Photo of Paul Monaghan Paul Monaghan Scottish National Party, Caithness, Sutherland and Easter Ross

To ask the Secretary of State for Energy and Climate Change, whether the London Power Tunnels Project is (a) on schedule for completion in 2018 and (b) within budget.

Photo of Andrea Leadsom Andrea Leadsom The Minister of State, Department of Energy and Climate Change

National Grid has said that:

  1. The London Power Tunnels Project is on schedule for completion in 2018 with all significant work completed in 2017 a year ahead of the original programme.

  2. The London Power Tunnels Project is currently within budget.