Department for Transport written question – answered at on 21 January 2016.
To ask the Secretary of State for Transport, what Network Rail maintenance, renewal or enhancement works that were planned to be carried out under blockade during the 2015-16 Christmas and New Year period were cancelled or deferred.
Network Rail has advised that of the schemes at the 80 highest priority worksites over the 2015/16 Christmas/New Year period, only one was cancelled – planned bridge works at Old Lodge Lane at Purley, which were cancelled due to high winds.