Department for Culture, Media and Sport written question – answered on 3rd November 2015.
To ask Her Majesty’s Government when and where the Mobile Infrastructure Project will be rolled out in Northern Ireland.
The Mobile Infrastructure Project is being rolled out in Northern Ireland up to the end of March 2016.
There are currently 7 masts in build phase. These are located in:
• Fermanagh and Omagh (2 sites)
• Mid Ulster (3 sites)
Planning permission was received for 4 sites. These sites are located in:
• Mid Ulster (3 sites)
Planning applications were submitted but decisions awaiting for 5 other sites. These are located in:
• Armagh, Banbridge and Craigavon
• Derry and Strabane District
• Fermanagh and Omagh (2 sites)
• Mid Ulster