Hinkley Point C Power Station

Department for Energy and Climate Change written question – answered on 23rd June 2015.

Alert me about debates like this

Photo of Paul Flynn Paul Flynn Labour, Newport West

To ask the Secretary of State for Energy and Climate Change, what estimate she has made of the cost of decommissioning and long-term radioactive waste management at the planned Hinkley Point C nuclear power plant.

Photo of Andrea Leadsom Andrea Leadsom The Minister of State, Department of Energy and Climate Change

The estimated decommissioning and long-term radioactive waste management costs for the Hinkley Point C nuclear power plant have been provided by NNB Generation Ltd and reviewed by the Department.

Based on these estimates, we anticipate that the costs will account for around £2 per megawatt hour of the strike price for this power station.