St Helena

House of Lords written question – answered at on 15 December 2014.

Alert me about debates like this

Photo of Lord Ashcroft Lord Ashcroft Conservative

To ask Her Majesty’s Government what progress has been made in the construction of the St Helena airport; what is the estimated date that the first aircraft could land; and whether the construction is within budget.

Photo of Baroness Northover Baroness Northover Baroness in Waiting (HM Household) (Whip), The Parliamentary Under-Secretary of State for International Development

Construction of the St Helena Airport is more than 60% complete. It is currently within budget and on target to open for commercial flights in early 2016.