Defence written question – answered at on 12 June 2014.
To ask the Secretary of State for Defence with reference to the answer of 18 December 2013, Official Report, column 636W, on defence: procurement, what the final costs are of establishing a Golo and running the tendering process.
The final cost of supporting our work on the Government Owned Contractor Operated (GOGO) competition is £7.4 million. This investment has provided valuable insight into the challenges involved in establishing a successful GOCO. The outputs from this work will be retained to inform any future GOCO competition should a decision be taken to re-examine this model as part of the continuing transformation of Defence Equipment and Support.