House of Lords written question – answered on 10 October 2013.
To ask Her Majesty’s Government what was the original budget estimate for building the airport on St Helena, and what is the current forecast cost.
The UK Government approved a grant of £201.5 million with an additional shared risk contingency of up to £10 million for the design and construction phase of the airport. The project is on track to deliver the construction phase within this budget.