To ask Her Majesty’s Government what progress has been made in the construction of the airport on St Helena.
Construction is progressing well and is currently on schedule to allow the airport to open in February 2016. Work on the major rock-fill embankment in Dry Gut to accommodate the runway is now 39% complete and construction of the terminal and services buildings commenced in August 2013.