To ask the Secretary of State for Transport what the additional capacity will be of the planned A14 toll road between Ellington and Girton.
Under the proposed scheme currently being consulted on, the Highways Agency are proposing a tolled route between Ellington and Brampton providing an additional 103 lane kilometres.
In addition, they are proposing to add a further (non-tolled) 18 lane kilometres between Brampton and Swavesey providing a total additional capacity of 121 lane kilometres.
Under the proposals the existing A14 through Huntingdon would be detrunked but maintains its existing capacity.