To ask the Secretary of State for Defence what the cost is of building and equipping for sea a (a) minesweeper, (b) destroyer, (c) frigate, (d) nuclear submarine and (e) Trident-equipped submarine; how many such vessels are in active service; and when each such vessel was commissioned.
The information requested is provided in the following table.
The costs provided are based on actual costs at the time they were incurred and therefore do not reflect current build costs. They cover those vessels that have achieved their In Service Date (ISD). Total costs of equipping the platforms (which is an ongoing process through life), including those associated with Government Furnished Equipment, are not held centrally and could be provided at only disproportionate cost,
ISDs have been provided as they more accurately reflect a ship's availability for ‘active service’ than commissioning dates.
Mine Countermeasure Vessels | ||
In service date | Build cost (£ million)(1) | |
Hunt Class | ||
HMS Ledbury | May 1981 | 31 |
HMS Cattistock | May 1982 | 32 |
HMS Brocklesby | October 1982 | 34 |
HMS Middleton | July 1984 | 36 |
HMS Chiddingfold | July 1984 | 37 |
HMS Hurworth | June 1985 | 39 |
HMS Atherstone | December 1986 | 42 |
HMS Quorn | January 1989 | 46 |
Sandown Class | ||
HMS Penzance | January 1998 | 49 |
HMS Pembroke | September 1998 | 48 |
HMS Grimsby | May 1999 | 48 |
HMS Bangor | December 1999 | 47 |
HMS Ramsey | July 2000 | 44 |
HMS Blyth | February 2001 | 44 |
HMS Shoreham | November 2001 | 45 |
(1) The figures quoted above do not represent the total cost of the vessels. Some figures, such as those for Government Furnished Equipment, are no longer held centrally for each ship and could be provided only at disproportionate cost. |
Type 45 Destroyers | |
In service date | |
HMS Daring | July 2010 |
HMS Dauntless | November 2010 |
HMS Diamond | August 2011 |
HMS Dragon | April 2012 |
HMS Defender | March 2013 |
HMS Duncan, the final ship in class, is expected to achieve her ISD in March 2014.
The unit production cost for a T45 is £633 million. This figure includes the cost of the T45 platform and the Sea Viper missile system, but does not include the development costs of the T45 programme.
Type 23 Frigates | ||
In service date | Build cost (£ million)(1) | |
HMS Argyll | November 1992 | 119 |
HMS Lancaster | February 1993 | 120 |
HMS Iron Duke | November 1993 | 110 |
HMS Monmouth | March 1994 | 112 |
HMS Westminster | March 1995 | 113 |
HMS Montrose | September 1995 | 117 |
HMS Northumberland | October 1995 | 115 |
HMS Richmond | July 1996 | 116 |
HMS Somerset | February 1997 | 114 |
HMS Sutherland | December 1997 | 144 |
HMS Kent | December 2000 | 108 |
HMS Portland | September 2001 | 92 |
HMS St Albans | September 2002 | 107 |
(1) The figures quoted above do not represent the total cost of the vessels. Some figures, such as those for Government Furnished Equipment, are no longer held centrally for each ship and could be provided only at disproportionate cost. |
Trafalgar Class submarines | |
In service date | |
HMS Tireless | October 1985 |
HMS Torbay | March 1987 |
HMS Trenchant | February 1989 |
HMS Talent | May 1990 |
HMS Triumph | November 1991 |
The build costs of these vessels are no longer held centrally and could be provided only at disproportionate cost.
Astute Class submarines
The first two (of seven) Astute Class submarines have achieved their ISD.
In service date | |
HMS Astute | April 2010 |
HMS Ambush | November 2012 |
HMS Artful, the third boat in class, is currently in build.
There is no unit cost for an Astute Class submarine as Boats one to three (Astute, Ambush, and Artful) were contracted as a batch with a total forecast cost of £3.4 billion, which includes cost of building the boats, the onboard communications system, and the tactical weapons system.
Vanguard Class submarines | |
In service date | |
HMS Vanguard | August 1992 |
HMS Victorious | March 1994 |
HMS Vigilant | February 1996 |
HMS Vengeance | March 1999 |
The total procurement cost for the four submarines was £3,587 million, which equates to approximately £897 million per submarine. This figure excludes the costs of the tactical and strategic weapons systems.
Yes2 people think so
No1 person thinks not
Would you like to ask a question like this yourself? Use our Freedom of Information site.