To ask the Secretary of State for Defence what estimate he has made of the cost of the Project Teutates Technology Development Centre at the Atomic Weapons Establishment Aldermaston; what the (a) total project costs and (b) projects costs incurred by the Government for Project Teutates has been in each year since 2010; and what he estimates such costs will be in each year to 2015.

Photo of Philip Dunne Philip Dunne The Parliamentary Under-Secretary of State for Defence

The approved cost for the construction of the Technology Development Centre is £48.7 million. The breakdown for each year since 2010 is given in the following table:

Financial year Costs at outturn prices (£ million)
2010-11 1.1
2011-12 11.7
2012-13 14.2
2013-14 (1)15.1
2014-15 (1)6.6
2015-16 (1)0.0
(1)Planned expenditure

I am withholding wider Project Teutates costs because disclosure would be likely to prejudice commercial interests and would impact on the formulation of Government policy.

Does this answer the above question?

Yes2 people think so

No2 people think not

Would you like to ask a question like this yourself? Use our Freedom of Information site.

Secretary of State

Secretary of State was originally the title given to the two officials who conducted the Royal Correspondence under Elizabeth I. Now it is the title held by some of the more important Government Ministers, for example the Secretary of State for Foreign Affairs.