St Helena: Airport

House of Lords written question – answered on 12th December 2012.

Alert me about debates like this

Photo of Lord Ashcroft Lord Ashcroft Conservative

To ask Her Majesty's Government what is the progress to date with the construction of St Helena airport.

Photo of Baroness Northover Baroness Northover Baroness in Waiting (HM Household) (Whip), Lords Spokesperson (Department for International Development)

Work on the St Helena Airport project is progressing well with the project on schedule and on budget. Initial work by the contractor to set up the logistics to support a major construction project on a remote island, to transport major construction equipment to the island, and then to transfer this to the airport site on Prosperous Bay Plain, is now complete. The contractor has constructed a temporary wharf in Rupert's Bay, established a regular shipping service from Walvis Bay in Namibia, constructed five temporary fuel tanks to provide 900,000 litres of storage and completed a 14 km-haul road to the airport site. Work is now under way on the permanent works with commencement of the major rock-fill embankment in Dry Gut.

Does this answer the above question?

Yes2 people think so

No0 people think not

Would you like to ask a question like this yourself? Use our Freedom of Information site.