To ask the Secretary of State for Transport on what date she expects all the rolling stock and infrastructure for Thameslink services to have been delivered; and for what reason the May 2012 update to her Department's Business Plan removed the reference to this being completed by the end of 2018.

Photo of Theresa Villiers Theresa Villiers The Minister of State, Department for Transport

The Department's objective is for all the rolling stock and infrastructure for Thameslink services to be delivered by December 2018.