Defence written question – answered on 10th July 2012.
To ask the Secretary of State for Defence
(1) whether the projects for the (a) Chinook fleet, (b) Apache fleet, (c) Apache extension, (d) Puma fleet, (e) Puma upgrade, (f) Warrior Armoured Fighting Vehicle, (g) Wildcat fleet, (h) Merlin fleet, (i) assessment phase for the Merlin marinisation, (j) Voyager air-to-air refueller and troop transporter, (k) A400M air transporter, (l) Air Seeker surveillance aircraft, (m) C17 strategic airlifter fleet, (n) Typhoon fleet and (o) joint strike fighter fleet are on time and on budget;
(2) what the (a) total cost and (b) length is of programmes for the (i) Chinook fleet, (ii) Apache fleet, (iii) Apache extension, (iv) Puma fleet, (v) Puma upgrade, (vi) Warrior Armoured Fighting Vehicle, (vii) Wildcat fleet, (viii) Merlin fleet, (ix) assessment phase for the Merlin marinisation, (x) Voyager air-to-air refueller and troop transporter, (xi) A400M air transporter, (xii) Air Seeker surveillance aircraft, (xiii) C17 strategic airlifter fleet, (xiv) Typhoon fleet and (xv) joint strike fighter fleet.
holding answer
For current performance against time and cost criteria for the Puma upgrade, Chinook fleet, Wildcat fleet, Merlin fleet, Voyager air-to-air refueller and troop transporter, A400M air transporter, Airseeker surveillance aircraft, Typhoon fleet and Joint Strike Fighter fleet, I refer the hon. Member to the “Major Projects Report 2011: Ministry of Defence”, published by the National Audit Office on
The Warrior Armoured Fighting Vehicle (Capability Sustainment programme) project is on time and on budget against its latest approval (as at
The eighth CI7 strategic airlift aircraft has been delivered and is in service.
The main investment decisions for Apache extension and Merlin Marinisation have not yet been made and until then, timelines and costs will not be confirmed. Apache fleet and Puma fleet are completed projects.
The latest planned length of the projects to completion (from
Project | Programme Length (Months) |
(a) Chinook fleet | 31 |
(b) Apache fleet | In-Service |
(c) Apache extension | Awaiting main investment decision |
(d) Puma fleet | In-Service |
(e) Puma upgrade | 38 |
(f) Warrior Armoured Fighting Vehicle - CSP | 79 |
(g) Wildcat fleet | 28 |
(h) Merlin fleet - Mk2 CSP | 26 |
(i) assessment phase of the Merlin marinisation | Awaiting main investment decision |
(j) Voyager air-to-air refueller and troop transporter | 25 |
(k) A400M air transporter | 35 |
(l) Airseeker surveillance aircraft | 31 |
(m) C17 strategic airlifter (8th aircraft) | 11 |
(n) Typhoon fleet | In-Service |
(o) Joint Strike Fighter fleet | Awaiting main investment decision |
With the exception of the eighth C17, the latest costs for those projects which are live and have passed their main investment decision are currently being validated by the National Audit Office. These will be published in the Major Projects Report 2012 in the autumn of this year. The eighth C17 will cost £200 million.