To ask the Secretary of State for Defence what the (a) original budget, (b) projected final cost, (c) expected timescales for delivery, (d) primary contractor and (e) identity of additional consortium members are in relation to the Typhoon Future Capability Programme.

Photo of Peter Luff Peter Luff The Parliamentary Under-Secretary of State for Defence

holding answer 14 November 2011

The original budget for the Typhoon Future Capability Programme was £449 million. The projected final cost is £458 million as at 31 March 2011. This increase is due to foreign exchange rate fluctuations. Both of these figures include the assessment, and demonstration and manufacture phases. The expected time scale for delivery, as set out in the 2011 Major Projects Review (in-service date) is June 2012. The primary contractor is the Eurofighter GmbH consortium, which comprises Alenia, BAE Systems and Cassidian.

Does this answer the above question?

Yes0 people think so

No0 people think not

Would you like to ask a question like this yourself? Use our Freedom of Information site.