To ask the Secretary of State for Defence what the (a) original budget, (b) projected final cost, (c) expected timescales for delivery, (d) primary contractor and (e) identity of additional consortium members are in relation to the A400M project.

Photo of Peter Luff Peter Luff The Parliamentary Under-Secretary of State for Defence

holding answer 14 November 2011

The initial approved cost for the A400M aircraft was £2.498 billion, and the current forecast cost to the UK of the A400M is £3.105 billion (including training and initial support). This increase is largely due to macro-economic factors including the foreign exchange rate against the Euro. The first UK A400M delivery is expected in September 2014 with the final UK aircraft delivery expected in September 2021. The A400M prime contractor is Airbus Military Sociedad Limitada. In addition to the United Kingdom, the other A400M partner nations are Belgium, France, Germany, Spain and Turkey.