House of Lords written question – answered at on 12 October 2011.
To ask Her Majesty's Government whether they consider that the proposed new Probation Case Management System, which is due to be completed by the end of March 2012, will be delivered on time.
To ask Her Majesty's Government what is the cost of the proposed new Probation Case Management System.
The deployment plan has been rescheduled. It is anticipated that the six-month deployment will now start in summer 2012. At this stage it is estimated that the cost of building and deploying the Probation Case Management System will be £47.733 million.
Yes0 people think so
No0 people think not
Would you like to ask a question like this yourself? Use our Freedom of Information site.