Motorways: Speed Limits

Transport written question – answered on 18th January 2011.

Alert me about debates like this

Photo of Greg Knight Greg Knight Chair, Procedure Committee

To ask the Secretary of State for Transport when he expects the M18 motorway to be clear of roadworks and temporary speed restrictions in both directions.

Photo of Mike Penning Mike Penning The Parliamentary Under-Secretary of State for Transport

There are currently four schemes being undertaken on the M18 between junctions 2 and 5 which are due to be completed by the end of March 2011.

This work includes three schemes to replace steel central reserve barriers, which are approaching the end of their design life, with new concrete central reserve barrier:

Junction 4 North (Waterton Bridge): commenced 20 December for 13 weeks.

Junction 3 North: commenced 18 October for 16 weeks.

Junction 2 to 3: commenced 20 December for 10 weeks.

In addition to the safety barrier works, work has also commenced at the A1 (M)/M18 Wadworth Interchange (M18 Junction 2) to install traffic signals. This is also due to be completed by the end of March 2011.

Does this answer the above question?