Astute Class Submarines

Defence written question – answered on 22nd July 2010.

Alert me about debates like this

Photo of Jeremy Corbyn Jeremy Corbyn Labour, Islington North

To ask the Secretary of State for Defence

(1) pursuant to the answer to the hon. Member for West Bromwich East of 15 June 2010, Official Report, column 347W, on Astute-class submarines, what progress has been made in re-baselining the drumbeat production level of the Astute-class submarines; and if he will make a statement;

(2) what his most recent estimate is of the future drumbeat level of production of Astute-class submarines; what he expects the (a) launch and (b) in-service dates to be of the remaining submarines; and if he will make a statement.

Photo of Peter Luff Peter Luff The Parliamentary Under-Secretary of State for Defence

holding answer 21 July 2010

All projects are being considered as part of the Strategic Defence and Security Review, and the outcome of this will be announced later this year.

The re-baselining work, which includes detailed joint planning and cost analysis by the Ministry of Defence (MOD) and BAE Systems Submarine Solutions, the prime contractor for the Astute Submarine Programme, is ongoing. The programme production timetable, including expected launch and in-service dates for the Astute class of submarines, can only be confirmed once this work has been completed, and MOD and HM Treasury re-approval has been obtained.

Does this answer the above question?

Yes1 person thinks so

No0 people think not

Would you like to ask a question like this yourself? Use our Freedom of Information site.