To ask the Chancellor of the Exchequer what the cost to the public purse had been of the Office for Government Commerce Heavy Hitter Programme Delivery Director service on the latest date for which figures are available; on which IT projects each consultant contracted under that service worked; and what payments have been made to each such consultant for work undertaken in connection with that service.
The Programme Delivery Directors (PDDs) project was part of a wider initiative, Executive Support Service, launched in 2005 to improve the success rate of major projects. Two consultants were deployed as Programme Delivery Directors, as set out in the table. The costs involved were recovered by the organisations concerned. Both appointments were made following a comprehensive value for money assessment.
Project name | Description | Period of time deployed: June 2006 - December 2007 | Daily r ate (£) | Total cost minus T and S (£) |
Youth Justice Board | Delivery Director Programme | 260 days | 1,100 | 273,000 |
OIS | Programme Delivery Director | 188 days | 1,200 | 217,000 |
Total | - | - | 490,000 |