Health written question – answered on 23 March 2009.
To ask the Secretary of State for Health what the initial estimated (a) cost and (b) delivery date for each ICT project initiated by his Department and its predecessor that cost more than £1 million was in each year since 2002.
The initial estimated costs and delivery dates of the information and communication technology (ICT) projects costing over £1 million that were initiated by the Department's Information Services function since 2002 are as follows:
Name of project | Initial estimated delivery date of project | Initial estimated cost of project (£ million) |
DOTP | October 2003 | 3.165 |
CSC Transformation | March 2004 | 9.1 |
Vista | April 2004 | 6.9 |
UNIFY1 | September 2005 | 2.179 |
SP2 Upgrade | February 2006 | 0.882 |
Quarry House LAN | March 2006 | 3.0 |
Delphi | June 2006 | 2.324 |
The Club | July 2006 | 1.949 |
Notes Upgrade | September 2006 | 1.993 |
UNIFY2 | April 2007 | 2.404 |
MEDBEN | February 2008 | 0.68 |
BMS | July 2008 | 10.5 |
Ref Costs 2008 | October 2008 | 0.875 |
Delphi 2 | January 2009 | 2.198 |
UNIFY Enhancement | November 2009 | 2.057 |
ACCEA | December 2009 | 1.5 |
The initial estimated costs and delivery dates of the ICT projects costing over £1 million that were undertaken by NHS Choices since 2002 are as follows:
Name of project | Initial estimated delivery date of project | Initial estimated cost of p roject (£ million) |
NHS Choices Technical Build | July 2007 | 3.7 |
The initial estimated costs and delivery dates of the ICT projects costing over £1 million that were undertaken by the Medicines and Healthcare products Regulatory Agency since 2002 are as follows:
Name of project | Initial estimated delivery date of project | Initial estimated cost of project (£ million) |
Sentinel Pharmacovigilance Casefolders | April 2006 | 1.342 |
Sentinel Server Upgrade | January 2009 | 3.5 |
Sentinel Component Software Development | June 2009 | 1.6 |
The ICT projects undertaken by NHS Connecting for Health are as follows:
Name of project | Initial estimated delivery date of project | Initial estimated cost of project (£ billion) |
National Programme for IT (NPfIT) | —(1) | (2)6.2 |
(1) NPfIT comprises a number of separate systems and services for which, as a whole, there is no single national completion date. (2 )This is the initial estimated cost of the core contracts. It was included in the estimated cost of the entire programme (£12.453 billion, at 2004-05 prices, including local and other costs) as reported by the National Audit Office in its June 2006 report on NPfIT. |
Cost of providing the above information
The cost of obtaining and collating the above information is approx £650. There are ICT elements to some of the business area programmes within the Department (e.g. Influenza Pandemic Preparedness) but the additional cost to obtain and collate this information would be disproportionate and exceed the £750 threshold for answers to parliamentary questions.