To ask the Secretary of State for Communities and Local Government how many homes have been assessed against the Code for Sustainable Homes since 1 May 2008; how many of these homes have been issued with (a) design stage and (b) post-construction certificates for levels (i) 3, (ii) 4 and (iii) 6 of the Code; and if she will break down these figures by type of landlord.

Photo of Iain Wright Iain Wright Parliamentary Under-Secretary (Department for Communities and Local Government)

There is approximately a six month time lag between registration and the design stage assessment, with a further time lag between the time the design is assessed and graded and when the home is built and the post-construction assessment carried out.

382 homes have been assessed against the Code for Sustainable Homes since 7 April 2008 (which is the date that we received data). Of these 337 received design stage certificates at code level 3 and none at code levels 4 and 6.

There are now 11 homes with post construction certificates; nine at code level 3 and two at code level 4. We do not currently hold data on whether the property is freehold or the status of the tenancy.