To ask the Secretary of State for Wales what the (a) start date, (b) original planned completion date, (c) current expected completion date, (d) planned cost and (e) current estimated cost is for each information technology project being undertaken by his Department; and if he will make a statement.

Photo of Huw Irranca-Davies Huw Irranca-Davies The Parliamentary Under-Secretary of State for Wales

My Department began work, in November 2007, on the development of new English and Welsh language websites.

The original completion date for the sites was the end of December 2007, however following revisions, the new websites are due to be launched by the end of January 2008.

The planned cost of the project is £29,611.