Roads: Repairs and Maintenance

Transport written question – answered at on 29 November 2007.

Alert me about debates like this

Photo of Theresa Villiers Theresa Villiers Shadow Secretary of State for Transport

To ask the Secretary of State for Transport if she will list each motorway and trunk road building project that has been submitted for the targeted programme of improvement scheme; and which schemes (a) have been (i) successful and (ii) unsuccessful and (b) are still being considered.

Photo of Tom Harris Tom Harris Parliamentary Under-Secretary (Department for Transport)

The following schemes have been approved for entry to the Targeted Programme of Improvements (TPI), since its inception. The six schemes shown as "suspended" were not prioritised for funding by the regions within their Regional Funding Allocations to 2015-16.

Project name Open to traffic
A1 Willowburn—Denwick Improvement Yes
A1 (M) Ferrybridge—Hook Moor Yes
A1 (M) Wetherby—Walshford Yes
A2 Bean—Cobham Phase 1 Bean—Pepperhill Yes
A2 Bean—Cobham Phase 2 Pepperhill—Cobham Under construction
A2/A282 Dartford Improvement Under construction
A5 Nesscliffe Bypass Yes
A5 Weeford—Fazeley Improvement Yes
A6 Great Glen Bypass Yes
A6 Rushden and Higham Ferrers Bypass Yes
A6 Rothwell—Desborough Bypass Yes
A6 Clapham Bypass Yes
A6 Alvaston Improvement Yes
A10 Wadesmill to Colliers End Bypass Yes
A11 Roudham Heath—Attleborough Improvement Yes
A14 Rookery Crossroads GSJ Yes
A21 Lamberhurst Bypass Yes
A23 Coulsdon Inner Relief Road Transferred to TfL
A27 Polegate Bypass Yes
A34 Chieveley/M4 Jet 13 Improvement Yes
A41 Aston Clinton Bypass Yes
A43 Silverstone Bypass (A43 M40—B4031 Dualling) Yes
A43 Whitfield Turn—Brackley Hatch Improvement (A43 M40—B4031 Dualling) Yes
A43 M40—B4031 Dualling Yes
A46 Newark—Lincoln Improvement Yes
A63 Selby Bypass Yes
A66 Stainburn and Great Clifton Bypass Yes
A120 Stansted to Braintree Improvement Yes
A249 Iwade—Queenborough Improvement (DBFO) Yes
A303 Stonehenge Under review
A421 Great Barford Bypass Yes
A500 City Road and Stoke Junction Improvement Yes
A500 Basford, Hough, Shavington Bypass Yes
A650 Bingley Relief Road Yes
A1033 Hedon Road Improvement Yes
M25J12-15 Widening Yes
M60 J5-8 Widening Yes
A11 Attleborough Bypass Yes
A11 Fiveways—Thetford Improvement In preparation
A47 Thorney Bypass Yes
M6 Carlisle to Guardsmill Extension Under construction
A63 Melton Grade Separated Junction Yes
A14 Haughley New St—Stowmarket Improvement Under construction
A3 Hindhead Improvement Under construction
A38 Dobwalls Bypass Under construction
A595 Parton—Lillyhall Improvement Under construction
A1 Peterborough—Blyth GSJ Under construction
M62 Junction 6 Improvement Under construction
A46 Newark—Widmerpool Improvement In preparation
A30 Bodmin Indian Queens Improvement Yes
A483 Pant—Llanymynech Bypass Suspended
A5117/A550 Deeside Park Junctions Improvement Under construction
A419 Blunsdon Bypass Under construction
A66 Temple Sowerby Bypass and Imp at Winderwath Yes
A1 Dishforth to Leeming Improvement (A1 Dishforth to Barton) In preparation
A1 Bramham—Wetherby (Including Wetherby BP) Under construction
A1 Leeming to Barton Improvement (A1 Dishforth to Barton) In preparation
A64 Rillington Bypass Suspended
M40/A404 Handy Cross Junction Improvement Yes
A47 Blofield to North Burlingham Dualling In preparation
A66 Greta Bridge to Stephen Bank Improvement Yes
A66 Carkin Moor to Scotch Corner Improvement Yes
A428 Caxton Common to Hardwick Improvement Yes
A30/A382 Merrymeet Junction Yes
A66 Long Newton Junction Under construction
A1 Stannington Junction Yes
A69 Haydon Bridge Bypass Under construction
A419 Commonhead Junction Yes
M4 Junction 18 Eastbound Diverge Yes
M5 Junctions 17—18a Northbound Climbing Lane (Hallen Hill) Yes
M5 Junctions 19-20 Southbound Climbing Lane (Naish Hill) Yes
M5 Junctions 19-20 Northbound Climbing Lane (Tickenham Hill) Yes
M1 J19/M6 Improvement In preparation
A14 Ellington—Fen Ditton Improvement In preparation
A57/A628 Mottram in Longdendale, Hollingworth and Tintwistle BP In preparation
A45/A46 Tollbar End Improvement In preparation
M1 Junction 6a to 10 Widening Under construction
M1 Junction 10 to 13 Widening In preparation
A1 Morpeth to Felton Dualling Suspended
A1 Adderstone to Belford Dualling Suspended
A1/A19/A1068 Seaton Burn Junction Improvement In preparation
A19/A184 Testos Grade Separated Junction In preparation
A505 Dunstable Northern Bypass (A5 to M1 Link) In preparation
A421 Bedford to M1 Junction 13 In preparation
A21 Tonbridge to Pembury Dualling In preparation
M40 Junction 15 (Longbridge Roundabout) In preparation
A64 Colton Lane GSJ Yes
A590 High and Low Newton Bypass Under construction
M20 Junction 10A In preparation
A30 Garland Cross to Chiverton Cross Suspended
A30 Temple to Higher Carblake Improvement Suspended
A27 Southerham to Beddingham Improvement Under construction
M1 J21-30 (Phase 1) Under construction
M1 J21-30 (Phase2) In preparation
M25 J1b-3 Widening (Section 3) Under construction
M25 J5-7 Widening (Section 2) In preparation
M25 J16-23 Widening (Section 1) In preparation
M25 J23-27 Widening (Section 5) In preparation
M25 J27-30 Widening (Section 4) In preparation
A21 Kippings Cross to Lamberhurst Improvements In preparation
A23 Handcross to Warninglid Widening In preparation
A453 Widening (M1 J24 to A52 Nottingham) In preparation
M25 Junction 28/A12 Brook Street Junction Improvement Under construction
M27 J11-J12 Climbing Lanes In preparation
M27 J3 To J4 Widening In preparation
M1 J30 to J31 Improvement In preparation
M1 J31 to J32 Widening Under construction
M1 J32 to J34 South Improvement In preparation
M1 J34 North to J37 Improvement In preparation
M1 J37 to J39 Improvement In preparation
M1 J39 to J42 Improvement In preparation
M1 J31-32 N/B Collector/Distributor In preparation
M62 J25 to J27 Improvement In preparation
M62 J27 to Jct 28 Improvement In preparation

The Highways Agency carries out a wide range of investigations to establish whether or not improvement schemes are required to address particular issues and problems on the trunk road network. A complete list of schemes which have been considered since the start of the Targeted Programme of Improvements could be provided only at disproportionate cost.

A number of schemes are currently being prepared and will be submitted in due course for a decision on whether they should be added to the roads programme. However, no applications are currently being considered.