To ask the hon. Member for North Devon, representing the House of Commons Commission what the current estimate for completed works on the new visitor entrance is; and what percentage this is of the original contract price.

Photo of Nick Harvey Nick Harvey Shadow Secretary of State for Defence

The latest forecast including contracted works costs, fitting out, fees and preliminary works is £8,727,500 against the original business case approval of £8,687,500. This is an increase of less than 1 per cent. There are a number of different contracts involved in the project. The latest valuation for works completed on the main contract as of 23 November 2006 is £4,303,660 and represents 101 per cent. of the original contract price for that element of the contract.

Does this answer the above question?

Yes1 person thinks so

No1 person thinks not

Would you like to ask a question like this yourself? Use our Freedom of Information site.