Naval Refit Contracts

Defence written question – answered on 14th March 2005.

Alert me about debates like this

Photo of Rachel Squire Rachel Squire Labour, Dunfermline West

To ask the Secretary of State for Defence what the contracted price was for the refit package for HMS Richmond placed with FSL.

Photo of Adam Ingram Adam Ingram Minister of State (Armed Forces), Ministry of Defence

holding answer 8 March 2005

The contracted price agreed with FSL for the refit package of HMS Richmond is commercially sensitive information and is, therefore, being withheld. However, it can be revealed that the total cost of the work, including the FSL refit and the installation of additional MOD supplied equipment, is in excess of £20 million.

Does this answer the above question?

Yes3 people think so

No3 people think not

Would you like to ask a question like this yourself? Use our Freedom of Information site.