– Scottish Parliament written question – answered at on 21 March 2011.
Question S3W-40351
To ask the Scottish Executive what the status is of the Forth Replacement Crossing Principal Contract procurement process.
The tender period for the Principal Contract has concluded successfully. Two valid and high quality bids have been received.
We can confirm the project costs will be fully met from the Scottish Government capital budget. Formal letters indicating an intention to award have been issued today and, subject to the mandatory standstill period, the contract will be awarded to the successful contractor in mid-April.
Yes2 people think so
No0 people think not
Would you like to ask a question like this yourself? Use our Freedom of Information site.