– Scottish Parliament written question – answered on 21st June 2007.

Alert me about debates like this

Photo of Jeremy Purvis Jeremy Purvis Liberal Democrat

Question S3W-866

To ask the Scottish Executive, further to the answer to question S3W-222 by Stewart Stevenson on 8 June 2007, what the current cost estimates are for the construction of the Borders railway.

Photo of Stewart Stevenson Stewart Stevenson Scottish National Party

The current cost estimate given by the Promoter in their Outline Business Case is £130.6 million at 2002 prices. This figure excludes Optimism Bias and includes the additional station at Stow. The promoter’s estimate is currently subject to review by Transport Scotland.