To ask the Scottish Executive what construction projects with a value of over £1 million are currently expected to be procured by the three water authorities over the next nine months.
I have asked the water authorities to provide a list of those construction contracts in excess of £1 million they expect to award in the next nine months. These are as follows:
North of Scotland Water Authority
Achiltibuie Water Supply
Cromarty Wastewater Treatment Plant
Munlochy Wastewater Treatment Plant
Stemster, Dunn, Haster, Reiss – new trunk main
Lochaber Mains Renewals
East Coast Mains Renewals
Balrobert to Oldtown Mains Renewal
Lochcarron Wastewater Treatment Plant
Inverness Sewer Rehabilitation
40" Mains Lintrathen to Clatto
Tayside Area Mains Renewals
Dundee (Clatto) Water Treatment Works
Kirkwall Wastewater secondary treatment
Keith Wastewater Treatment Plant Upgrade & Newmill Wastewater Treatment Plant
Cruden Bay Wastewater Treatment Plant & Combined Sewer Overflow
Grampian Mains Renewal Programme - 00/01 + 01/02
Grampian Combined Sewer Overflow Programme
Water Quality Improvements – Distribution Systems
Stornoway Water Treatment Works & Distribution
Forehill Water Treatment Works & Distribution
Mainland Augmentation – Boardhouse Ph 3
Invercannie Water Treatment Works & Distribution
Turriff Water Treatment Works & Distribution
North Coast Regional Scheme
West of Scotland Water Authority
Glasgow – Acre Road Sewer
Meadowhead – Gailes Storm Water Outfall Sewer
Maidens Kirkoswald Turnberry Sewerage Scheme
Milton, Bowling to Castlegreen (Dumbarton) Sewer
Old Kilpatrick to Dalmuir Sewer
Newton Stewart Wastewater Treatment Works
Stranraer Wastewater Treatment Works
Carradale Wastewater Treatment Facilities
Cove and Kilcreggan Wastewater Treatment Facilities
Inveraray Wastewater Treatment Facilities
Kames and Tighnabruaich Wastewater Treatment Facilities
Machrihanish Drumlemble Wastewater Treatment Facilities
Millport Wastewater Treatment Facilities
Cairndow Water Supply
Taynuilt Water Supply
Peden Water Supply
East of Scotland Water Authority
ESW Orthophosphate dosing
Stirling Lovers Walk Pumping Station
Culross Main Drainage
Figgate Burn Drainage Upgrade
Penicuik Wastewater Treatment Works
Penicuik/N. Borders Water Supply
Dunfermline Trunk Sewer Duplication
Alloa West Sewers
Cupar Sludge Treatment Centre