Road Improvements (A84)

– in the Scottish Parliament at on 7 March 2019.

Alert me about debates like this

Photo of Dean Lockhart Dean Lockhart Conservative

3. To ask the Scottish Government when the feasibility study on junction improvements on the A84 near Blair Drummond Safari Park will be completed. (S5O-02965)

Photo of Paul Wheelhouse Paul Wheelhouse Scottish National Party

Transport Scotland commissioned its operating company to undertake a feasibility study and to outline the design for potential improvements at the location. That has taken longer than anticipated, as new information relating to historical accidents came to light during the final evaluation stage. That information is currently being reviewed to see how it relates to the completion of the study. The Cabinet Secretary for Transport, Infrastructure and Connectivity, Michael Matheson, has asked Transport Scotland officials to conclude the report at the earliest opportunity.

Photo of Dean Lockhart Dean Lockhart Conservative

I thank the minister for that response and update. Community representatives first met in December 2017 to discuss options to improve safety at the junction. The feasibility study was meant to appear in summer 2018 but has since faced the delays that the minister mentioned. Does he share my frustration about the delay to the report and does he share the concerns of local communities about the junction?

Photo of Paul Wheelhouse Paul Wheelhouse Scottish National Party

First, I absolutely recognise the strong community interest in the issue. I know that Mr Lockhart and Mr Crawford have raised the issue in the course of their work and I understand the frustration of the local community about any delay to such a key study. As I said, the cabinet secretary is keen for the final report to be presented to him at the earliest opportunity and I am sure that he will be keen to communicate it to Mr Lockhart.

Photo of Bruce Crawford Bruce Crawford Scottish National Party

Although I am grateful for the information that the minister provided to Dean Lockhart, I hope that he will understand my disappointment that it has taken a parliamentary question for the delay to emerge from Transport Scotland. In October last year, I was informed that the study would be available in a number of weeks, and I informed the community of that response.

I hope that the minister will also understand that there will be considerable frustration about the delay in the Blair Drummond community, because the people there have been gallantly campaigning on this important road safety issue for a number of years.

Photo of Paul Wheelhouse Paul Wheelhouse Scottish National Party

I absolutely accept the concerns that Mr Crawford raised and—for what it is worth—I apologise to Mr Crawford for the delay in the production of the report. As I explained in my initial answer to Mr Lockhart, the reason for the delay is the presentation of additional accident data. I hope that Mr Crawford understands the need to take that on board to ensure that the final report reflects that data if necessary. However, I am sorry that the delay was not communicated to Mr Crawford and that he has had to wait to hear that news today. I am sure that Mr Matheson will be keen to ensure that all members who have an interest in the issue are communicated with as soon as possible once the final report has been produced.