Question proposed, That the clause stand part of the Bill.

Photo of Karen Buck Karen Buck Labour, Westminster North

With this, it will be convenient to consider the following:

That schedule 15 be the Fifteenth schedule to the Bill.

That schedule 16 be the Sixteenth schedule to the Bill.

Photo of Nusrat Ghani Nusrat Ghani Parliamentary Under-Secretary (Department for Transport), Assistant Whip (HM Treasury)

Clause 13 introduces schedules 15 and 16, which give the Secretary of State powers to take temporary possession of land within the Bill limits for the purpose of phase 2a. The land listed in the table in schedule 16 can be taken only temporarily and not acquired, except for subsoil and rights or restrictive covenants over the land.

Schedule 15 sets out the procedure, including the notice required, the payment of compensation to effective landowners, the suspension of private rights and rights of access over the land during the period of temporary possession and arrangements for the restoration and return of the land.

Question put and agreed to.

Clause 13 accordingly ordered to stand part of the Bill.