Clause 2 concerns further provision about works. It is not exactly a very exciting title, but it authorises the nominated undertaker to carry out any ancillary works that are necessary for the construction and maintenance of phase 1 of HS2, so long as such works remain within the limits as shown on the plans. This could be either railway works or, as stated in subsection (3),

“landscaping and other works to mitigate any adverse effects of the construction”.

Again, this is a standard clause for works Bills. Subsection (4) introduces schedule 2, which contains,

“further and supplementary provision about works”.

This schedule allows certain protective works, such as the preservation of buildings, tree management and so on, to be carried out for works authorised by the Bill. Schedule 2 also describes how the nominated undertaker can access properties along the route to carry out works and provide safeguards for those property owners.

Subsection (5) allows the nominated undertaker to divert the electricity lines identified in schedule 3 and carry out the ancillary works required for these diversions. I am sorry that I could not make it more exciting, but I beg to move that clause 2 stands part of the Bill.

Photo of Andy McDonald Andy McDonald Shadow Minister (Transport)

I simply endorse the comments of the Minister and congratulate him on making something very dull very exciting—I enjoyed what he had to say.

Question put and agreed to.

Clause 2 accordingly ordered to stand part of the Bill.